Project Name |
Project Description |
Estimated/ |
Permits/Easements |
Preliminary Engineering |
Construction |
|
|
|
|
Actual Cost |
|
|
|
|
1 |
Square Circle Road |
Paved approx. 1.89 miles of dirt road. |
$490,151 |
|
|
Completed Aug. 6, 2002. |
|
|
|
|
|
|
|
|
|
2 |
Mt Zion |
Paved approx. 3.62 miles of dirt road. |
$691,534 |
|
|
Completed September 10, 2004 |
|
|
|
|
|
|
|
Paved w Fields Cemetery Rd. |
|
3 |
Fields Cemetery Road |
|
|
|
|
Paved w Mt. Zion Rd. |
|
|
|
|
|
|
|
|
|
4 |
Old Graniteville Road |
Paved approx. 0.43 miles of dirt road |
$721,832 |
|
|
Completed July 30, 2004. |
|
|
|
adjacent to Rainbow Falls Road. |
|
|
|
Paved w Springdale & Sandy Ridge Rd. |
|
5 |
Springdale Road |
Paved approx. 1.55 miles of dirt road from |
|
|
|
Paved with Old Graniteville and Sandy Ridge Roads. |
|
|
|
Bettis Academy Road to Whaley Pond Road. |
|
|
|
|
|
6 |
Sandy Ridge Rd |
Paved approx. 1.00 miles of dirt road from |
|
|
|
Paved with Old Graniteville and Springdale Rds. |
|
|
|
Rainbow Falls Whaley Pond Road |
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
Tomahawk Drive |
Paved approx. 0.49 miles of dirt road from |
$132,735 |
|
|
Completed January 1, 2003. |
|
|
|
Old Friar Road to Lake Shore. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Avalon Lane |
Pave approx.0.63 miles of dirt road from |
|
Deleted |
Deleted |
Deleted by Citizen's Request |
|
|
|
Augusta Road to Parker Drive. |
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Powerhouse Road |
Paved approx. 1.94 miles of dirt road from |
$641,773 |
|
|
Completed December 23, 2003. |
|
|
|
Old Aiken Road to Cherokee Rd. |
|
|
|
Paved w Bradleyville Rd. |
|
9 |
Bradleyville Road |
Paved approx. 0.44 miles of dirt road from |
|
|
|
Paved with Powerhouse Rd. |
|
|
|
Woodberry Ln. to Powerhouse Rd. |
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
Hancock Road |
Paved approx 2.05 miles of dirt road from |
$776,526 |
|
|
Completed August 18, 2003. |
|
|
|
Vaucluse Road to Outing Club Rd. |
|
|
|
Paved w Washboard Rd. |
|
11 |
Washboard Road |
Paved approx. 1.03 miles of dirt road from |
|
|
|
Paved with Hancock Road |
|
|
|
Vaucluse Road to Good Springs Rd. |
|
|
|
|
|
|
|
|
|
|
|
|
|
12 |
Confederate Road |
Paved approx. 0.86 miles of dirt road from |
$258,864 |
|
|
Completed September 3, 2003. |
|
|
|
Frontage Road to Good Springs Rd. |
|
|
|
|
|
|
|
|
|
|
|
|
|
13 |
Waterwheel Road |
Paved approx. 2.00 miles of dirt road from |
$397,898 |
|
Complete |
Completed Jan. 27, 2006 |
|
|
|
Salley Road to Wagener Trail Rd. |
|
|
|
|
|
|
|
|
|
|
|
|
|
14 |
Mayfield Road |
Paved approx. 1.99 miles of dirt road from |
$415,894 |
|
|
Completed September 3, 2003 |
|
|
|
Edgefield Hwy to existing pavement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Olive Heights |
Pave approx. 0.70 miles of dirt road from |
|
Deleted |
Deleted |
Deleted August 20, 2002 by Council. |
|
|
|
Chalk Bed Road from Chalk Bed Road to |
|
|
|
Due to right-of-way issues. |
|
|
|
Old Cherokee Indian Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
Gum Swamp Road |
Paved from Hwy 5 for 3.05 miles. |
$300,063 |
|
|
Completed October 17, 2002. |
|
|
|
|
|
|
|
|
|
|
Westbrook Road |
From State Rd S-2-5 (Old Jackson Hwy) to |
|
Deleted |
Deleted |
Deleted July 17, 2002 by Council. |
|
|
|
S-2-905 (Old Nail Rd) 1.5 mi. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
|
Blackstone Camp Road |
From SC 125 to S-2-145 ( Storm Branch Road) |
|
Deleted |
Deleted |
Deleted August 20, 2002 by Council. |
|
|
|
2.2 mi. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
16 |
Nantuckett Road |
From S-2-14( Hollow Creek Rd) to |
$477,000 |
22 Easements needed: |
|
|
|
|
|
River Road (C-895) - 1.5 mi. |
|
13 Easements signed |
|
|
|
|
|
|
|
1- No; 0 Non-responses |
|
|
|
|
|
|
|
Road Swap with SCDOT approved |
|
|
|
|
|
|
|
and completed as of June 23, 2005. |
|
|
|
|
|
|
|
|
|
|
|
17 |
Boyd Pond Road |
Paved from S-2-145 ( Storm Branch) to SC 302 |
$529,574 |
|
|
Completed May 10, 2004. |
|
|
|
2.8 mi. |
|
|
|
|
|
|
|
|
|
|
|
|
|
18 |
Bethcar Church Road |
From S-2-75 ( Camp Rawls) to SC 39, 2.1 mi. |
$1,095,856 |
Complete |
Complete |
Completed November 7, 2005. |
|
|
|
from S-302 to Paved S-246, 2.1 mi. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Redcliff Road |
From SC 125 to S-2-580 (Hammond Hill) 1.05 mi. |
|
Deleted |
Deleted |
Deleted by citizens. |
|
|
|
|
|
|
|
|
|
19 |
Brier Patch Lane |
Paved from S-2-87(Pine Log) to S-2-778 |
$687,662 |
|
|
Completed October 8, 2004. |
|
|
|
(Herndon Dairy) 3 mi. |
|
|
|
|
|
|
|
|
|
|
|
|
|
20 |
Flowing Well Road |
Pave 3.7 mi from HWY 302 to the gas line. |
$712,526 |
Complete |
Complete. |
Clearing and grubbing work 100% complete. |
|
|
|
|
|
Road Swap with SCDOT approved |
|
Pipe Installation work 100% complete. |
|
|
|
|
|
and completed as of June 23, 2005. |
|
Subgrade 100% complete. Placing Sand Clay Base. |
|
|
|
|
|
|
|
|
|
21 |
Anderson Pond Road |
Pave 4.25 mi from Silver Bluff Rd to Chime |
$1,351,500 |
Letters to Owners |
|
|
|
|
|
Bell Church Road |
|
14 Easements needed: |
|
|
|
|
|
|
|
10 Yes, 4 No |
|
|
|
|
|
|
|
8 easements signed. |
|
|
|
|
|
|
|
|
|
|
|
|
Medwell Hill Road |
Pave 0.80 mi from Whiskey Rd to Chime Bell |
|
Deleted |
Deleted |
Deleted by Council July 19, 2005. |
|
|
|
Church Road. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
22 |
Mull Street |
Paved 0.30 mi from Griffin Ave to Mull Street |
$61,243 |
|
|
Completed December 15, 2003. |
|
|
|
S-2-1674. |
|
|
|
|
|
|
|
|
|
|
|
|
|
23 |
Andrews Circle |
Paved 4.10 miles from Old Barnwell Rd to Old |
$1,033,240 |
|
|
Completed July 6, 2005. |
|
|
|
Barnwell Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Pitts Branch Rd |
Pave 2.20 mi from Mt. Pleasant Rd to Engineer Road. |
|
Deleted |
Deleted |
Deleted November 19, 2002 by Council. |
|
|
|
|
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
24 |
Cummings Road |
Paved approximately 1.90 mi from Mt. Calvary |
$554,610 |
|
|
Completed May 18, 2005 |
|
|
|
Rd. to Bogeyville Rd |
|
|
|
|
|
|
|
|
|
|
|
|
|
25 |
Satcher Pond Road |
Pave approx. 1.66 miles of dirt road from Old Four |
$456,300 |
17 Easements needed: |
Surveying 100% Complete |
|
|
|
|
Notch Road to Columbia Hwy. |
|
17 Easements in hand. |
Engineering 100% Complete |
|
|
|
|
|
|
|
|
|
|
26 |
Keys Pond Road |
Paved approx. 5.05 miles of dirt road from |
$1,001,323 |
|
|
Completed Feb. 28, 2005 |
|
|
|
Cumbee Trail Road to Columbia Hwy. |
|
|
|
|
|
|
|
|
|
|
|
|
|
27 |
Fulmer Road |
Paved approx 1.70 miles of dirt road from |
$330,666 |
|
|
Completed April 16, 2004. |
|
|
|
Hamelin Road to U. S. 1 Columbia Hwy. |
|
|
|
|
|
|
|
|
|
|
|
|
|
28 |
Cumbee Trail Road |
Paved approx. 4.80 miles of dirt road from US |
$1,096,317 |
|
|
Completed Feb. 28, 2005 |
|
|
|
1 to state portion of Cumbee Trail S-2-2178. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Cato Road |
Pave approx. 0.90 miles of dirt road from |
|
Deleted |
Deleted |
Deleted November 19, 2002 by Council. |
|
|
|
Columbia Hwy to Farm View Road. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
29 |
Old Chalk Bed Road |
Pave approx.5.10 miles of dirt road from SC |
$1,083,523 |
|
|
Completed September 13, 2005. |
|
|
|
Hwy 39 to the Lexington County line. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Gunter Pond Road |
Pave approx. 4.70 miles of dirt road from Old |
|
Deleted |
Deleted |
Deleted August 19, 2003 by Council. |
|
|
|
Ninety - Six Indian Trail Road to New Holland Road. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
30 |
Browns Pond Road |
Pave approx 3.50 miles of dirt road from Bubba |
$748,758 |
Complete |
Complete |
Sand clay base 100% complete |
|
|
|
Gunter Road to S.C. Hwy 302. |
|
|
|
Paving 50% complete |
|
|
|
|
|
|
|
|
|
31 |
Vintage Vale Road |
Paved approx. 1.50 miles of dirt road from |
$425,141 |
Complete |
Complete |
Completed January 27, 2006 |
|
|
|
Beaver Dam Road to Snipes Pond Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
32 |
Day Road |
Paved approx. 1.70 miles of dirt road from Wire |
$429,983 |
Complete |
Complete. |
Completed January 27, 2006 |
|
|
|
Road to New Bridge Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
33 |
Joyce Branch Road |
Pave approx. 1.70 miles of dirt road from New Bridge |
$331,080 |
Complete |
Complete |
Final Inspection held January 24, 2006. |
|
|
|
Road from New Bridge Road to Cook Bridge Road. |
|
|
|
Contractor working punchlist. |
|
|
|
|
|
|
|
|
|
|
Merritts Bridge Road |
Pave approx. 2.35 miles of dirt road from Poplar |
|
Deleted |
Deleted |
Deleted by Council, July 19, 2005. |
|
|
|
Spring Road to Poplar Spring Road. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
|
Cedar Creek Road |
Pave approx. 2.40 miles of dirt road from Burkelo |
|
Deleted |
Deleted |
Deleted December 22, 2004 by Council. |
|
|
|
Road to Camp Rawls Road. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
34 |
Old Tory Trail |
Pave approx. 3.35 miles of dirt road from |
$887,750 |
19 Easements needed: |
Surveying 100% Complete |
Contractor Selected. |
|
|
|
Hatchaway Bridge Road to Mackey Scott Road. |
|
19 Easements signed. |
Engineering 100% Complete. |
Notice to proceed March 7, 2006. |
|
|
|
|
|
|
|
|
|
35 |
Perron Garvin Road |
Pave approx. 1.75 miles of dirt road from Bethcar |
$511,875 |
Complete |
Complete |
Bid Opened February 20, 2006. |
|
|
|
Church Road to Wagener Road. |
|
|
|
Preconstruction meeting held March 28, 2006 |
|
|
|
|
|
|
|
Notice to proceed April 24, 2006 |
|
|
|
|
|
|
|
|
|
36 |
Centerwood Road |
Pave approx. 2.50 miles of dirt road from Oak Ridge |
$795,000 |
2 Easements needed: |
|
|
|
|
|
Club Road to Beck Road. |
|
2 Easements signed. |
|
|
|
|
|
|
|
|
|
|
|
|
Cedar Branch Road |
Pave approx. 2.00 miles of dirt road from Cedar |
|
Deleted |
Deleted |
Deleted April 6, 2005 by Council. |
|
|
|
Branch Road S - 576 to Old Tory Trail Road. |
|
|
|
Due to right-of-way issues. |
|
|
|
|
|
|
|
|
|
|
Big Tree Road |
Pave approx. 1.20 miles of dirt road from Hwy |
|
Deleted |
Deleted |
Deleted September 20, 2005 by Council. |
|
|
|
394 to Hoss Ln. |
|
|
|
Due to right-of-way issues |
|
|
|
|
|
|
|
|
|
37 |
Washington Road |
Pave approx. 0.90 miles of dirt road from Festival |
$286,200 |
Letters to Owners. |
Engineer selected. |
|
|
|
|
Trail Road to Wagener Road. |
|
6 Easements needed: |
Engineering 75% complete |
|
|
|
|
|
|
5 Easements signed |
|
|
|
|
|
|
|
1 SCDOT |
|
|
|
|
|
|
|
|
|
|
|
38 |
Union Academy Road |
Pave approx. 1.30 miles of dirt road from Salley |
$413,400 |
14 Easements needed: |
|
|
|
|
|
Road to Windsor Road. Recommendation to Council |
|
13 Yes, 1 No |
|
|
|
|
|
to delete remaining portion of roadway. Unable to |
|
6 signed documents in hand. |
|
|
|
|
|
obtain necessary easements. |
|
46% complete |
|
|
|
|
|
|
|
|
|
|
|
39 |
Union Hill Road |
Pave approx. 1.30 miles of dirt road from |
$380,250 |
14 Easements needed: |
Surveying 100% Complete. |
Bid opening scheduled for April 6, 2006 |
|
|
|
Hollow Creek Road to Joe Scott Road. |
|
14 Easements signed. |
Engineering 100% Complete. |
|
|
|
|
|
|
|
|
|
|
40 |
Gregory Road |
Pave approx. 0.35 miles of dirt road from |
|
|
|
Road S-980 already paved. |
|
|
|
Gregory S-2-1980 to Shiloh Church Road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
41 |
Association Central Building Rd |
Pave approx. 0.15 miles of dirt road from |
$47,700 |
6 Easements needed: |
|
|
|
|
|
Anderson Pond Road to Dead End. |
|
3 Yes, 3 No |
|
|
|
|
|
|
|
|
|
|
|
42 |
Snipes Road |
Pave approx. 0.40 miles of dirt from |
$117,000 |
Existing 50 feet of right-of-way. |
Surveying 100% Complete. |
Bid opening scheduled for April 6, 2006 |
|
|
|
Redd Branch Road to Redd Branch Road. |
|
|
Engineering 100% Complete. |
|
|
|
|
|
|
|
|
|
|
43 |
Browns Pond Road - (State Portion) |
Pave 0.90 miles from Hwy 113 to E. Z. Collum Rd. |
$286,200 |
5 easements needed. |
|
|
|
|
|
Requested by Council. |
|
5 Yes; 0 No |
|
|
|
|
|
|
|
5 signed documents in hand. |
|
|
|
|
|
|
|
|
|
|
|
44 |
Flowing Well Road - (State Portion) |
Pave 1.60 miles from Gas Line to New Holland Rd. |
$658,000 |
3 easements needed: |
|
|
|
|
|
|
|
2 Yes; 1 No |
|
|
|
|
|
|
|
|
|